Southern California Contractors Association
 
 
  MENU
  Home
  Contact us
  What we do
  Events & Meetings
  Industry Resources
  Safety Resources

  SCCA Magazine
  JULY-AUG 2011 Issue
  MAY-JUNE 2011 Issue
  MAR-APR 2011 Issue
  JAN-FEB 2011 Issue
  2010 ISSUES
  Editorial Calendar
  Insertion Order
  Contact Us


 
 
Contractors’ expectations are often disappointed by rejections of their lowest bids in favor of a higher bidNon-responsive bid? from a competitor when the public entity declares the lowest bid
is non-responsive or the bidder is non-responsible. But there is an important distinction between the two that impacts the bidder’s rights. In order to avoid a loss of due process and, potentially, award of a public works project, it’s important for contractors to understand their rights, and act quickly.

The law requires a public entity to provide a contractor a due process hearing when the public entity rejects the contractor’s bid on the basis that the contractor is non-responsible. However, there is no right to a due process hearing when the public entity has merely found the contractor’s bid to be non-
responsive. Unfortunately, to avoid the due process hearing requirement, public entities have been known to notify bidders that their bids were non-responsive, when, in fact, the public entity had determined that the lowest bid contractor was non-responsible.

In a recent case, Great West Contractors v. Irvine Unified School District, the Court of Appeal said that an erroneous characterization of a bid as non-responsive when the bidder has, in fact, been found non-responsible, allows public entities to “circumvent public contracting statutes and do so without affording [the affected] bidder a hearing.”

Non-responsive bid or non-responsible bidder?
What is the difference between a non-responsive bid and a non-responsible bidder, and how can you tell which is the actual reason a bid was rejected? According to the appellate court, a general rule of thumb is that responsiveness can usually be determined by looking
solely at the bid and the bid request, without resort to any additional information, references, or past performance.

If the bid offers to build exactly what the bid package requests, the bid is responsive. If the bid varies from the bid request, it is non-responsive. For example, if the bid package requests acquisition of a particular system by purchase only, and the bid offers to lease the system to the public entity, the bid is non-responsive and may be rejected without a due process hearing.

If, however, the contractor’s bid offers to build exactly what was requested, and the bid is rejected as non-responsive, it is possibly an attempt by the public entity to circumvent the Public Contract Code and award the contract to a favored contractor for illegitimate reasons. Responsibility generally requires a public entity to investigate facts and circumstances that are not apparent on the face of the bid, assessing the reputation of the bidder, among other factors. Public Contract Code 1103 defines a “responsible bidder” as “a bidder who has demonstrated the attribute of trustworthiness, as well as quality, fitness, capacity and experience to satisfactorily perform the public works contract.”

Because a finding of non-responsibility can adversely affect the contractor’s public image and cause damage beyond the rejection of its bid on the project at issue, due process requires the public entity to notify the contractor and provide an opportunity for the contractor to respond and rebut the finding. Lowest bid contractors whose responsive bids are rejected as non-responsive should promptly seek legal advice if they think the
rejection of the bid was improperly characterized to avoid a due process hearing.

-By Eric N. Kibel, senor associate with Lanak & Hanna. He can be reached at (714) 550-0418 or www.lanak-hanna.com
 
 
 
  Southern California Contractors Association

Copyright 2011 by Southern California Contractors Association. All rights reserved.